The site has been cleared and the construction begins on the new Boys Dormitory. Site work being done by J.A.M. Construction Co., Inc. of Middletown, RI
Clearing site
Installing the drains
Electrical power feeds are installed. Electrical work is being done by Wayne J. Griffin Electric, Inc. of Holliston, MA.
Footing Layout
Footings formed
Footings for the foundations are formed and poured with reinforcing rod inserted and forms stripped. Concrete foundation and concrete walls formed, poured and stripped. Foundation work and concrete walls being done by S & S Concrete Form Construction of Swansea, MA. Concrete provided by Cardi Materials, LLC of Warwick, RI.
Footings formed and poured.
Transformer installed and foundation walls formed, poured and stripped.
Preparing to pour basement walls
Installing footing drains
Rebar walls
Stripping basement walls
Damproofing foundation
Preparing to dig the elevator pit
Beginning the interior footings
Backfilling the foundations on the north and south sides of the West end of the building.
Pouring the interior piers and footings for columns for 1st floor deck
More footings for the deck, and the elevator pit to the right.