| Project: Wall
Restoration |
Client:
Gaudet Middle School
Middletown, Rhode Island |
Architect
Newport Collaborative Architects, Inc., Newport,
RI |
Delivery Method:
General Contracting |
Size:
4,000 SF
|
Duration:
Three Months |
|
|
| Back |
|
Advanced Building Concepts' value
engineering recommendation to modify
panel-mounting procedures, reduced
construction costs and time by 10% on the Gaudet Middle School wall restoration
project. An existing masonry veneer wall
system was demolished, and a new composite
metal panel system was installed, with the
introduction of windows into exterior walls
to enhance natural lighting in the school
building.
After removal of the masonry veneer, the
masonry backup wall was found to be in poor
structural condition. In collaboration with
the project architect, ABC designed and
installed a steel curtain wall to supplement
the existing back-up wall, at no cost change
to the owner.
The three-month project was completed on
schedule in time for a fall school opening.
|
|

|
|